Wyandot Solar
juwi solar developed, designed and built the Wyandot Solar Energy Facility, a 12.6 megawatt (DC) solar PV facility located in Upper Sandusky, Ohio. In June 2009 juwi solar’s subsidiary executed a 20-year PPA with AEP Ohio. Construction commenced in the fourth quarter of 2009, and the project achieved commercial operation in May 2010.
- juwi solar’s construction group, together with a leading Ohio-based subcontractor, commenced construction in October 2009
- Includes 159,200 ground-mounted, thin-film solar panels on 77-acre plot of land
- Commercial operation occurred on May 26, 2010
- In September 2009, juwi solar transferred its ownership rights in the project to PSEG Solar Source
- Energy and REC off-taker is AEP Ohio
- juwi solar is currently operating, maintaining and monitoring the project on behalf of PSEG Solar Source
- November 03, 2009
- December 13, 2009
- January 07, 2009
- March 9, 2010
- April 19, 2010
- May 3, 2010
- September 18, 2010
- October 18, 2010